Construction of Flood Control Structure (Gabion) at Pampanga River, Barangay Bugnan, Gabaldon, Nueva Ecija
Location
Bugnan, Gabaldon, Nueva Ecija
Central Luzon
ZIP: 3007
15.471020, 121.301700
Project Cost
₱88M
₱88,397,389.39
Project Timeline
Start Date
February 15, 2023
Wed, Feb 15, 2023
Actual Start
February 15, 2023
Wed, Feb 15, 2023
Target Completion
May 23, 2023
Tue, May 23, 2023
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
Contractor
1 contractor