Rehabilitation of existing Dike along Lucung River, (Culatingan Section, Left Bank), Concepcion, Tarlac
Location
Culatingan, Concepcion, Tarlac
Central Luzon
ZIP: 2316
15.332480, 120.731040
Project Cost
₱48M
₱48,342,638.69
Project Timeline
Start Date
March 23, 2022
Wed, Mar 23, 2022
Actual Start
March 23, 2022
Wed, Mar 23, 2022
Target Completion
October 15, 2022
Sat, Oct 15, 2022
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates