Construction of Flood Control Structure at Barangay Pagala, Baliuag, Bulacan (K003+161 to K003+461)
Location
Pagala, Baliuag, Bulacan
Central Luzon
ZIP: 3006
14.976819, 120.884298
Project Cost
₱72M
₱71,915,112.64
Project Timeline
Start Date
March 27, 2023
Mon, Mar 27, 2023
Actual Start
March 27, 2023
Mon, Mar 27, 2023
Target Completion
December 05, 2023
Tue, Dec 05, 2023
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project
Project Updates
1 / 1
Use arrow keys to navigate • Press Esc to close
Loading comments...