Construction of Flood Control Structure Along Marilao River, Sta. 09 + 855 - Sta. 10 + 010, Marilao, Bulacan
Location
Marilao, Bulacan
Central Luzon
ZIP: 3019
14.768000, 120.955000
Project Cost
₱58M
₱57,899,228.21
Project Timeline
Start Date
February 21, 2023
Tue, Feb 21, 2023
Actual Start
February 21, 2023
Tue, Feb 21, 2023
Target Completion
October 19, 2023
Thu, Oct 19, 2023
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
Contractor
1 contractor