Construction of Flood Control Structure at Barangay Piel, Baliuag, Bulacan (K003+690 to K003+990)
Location
Piel, Baliuag, Bulacan
Central Luzon
ZIP: 3006
14.984714, 120.880856
Project Cost
₱72M
₱72,374,362.28
Project Timeline
Start Date
March 27, 2023
Mon, Mar 27, 2023
Actual Start
March 27, 2023
Mon, Mar 27, 2023
Target Completion
December 04, 2023
Mon, Dec 04, 2023
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
Contractor
1 contractor