Improvement of Waterways and Flood Control Structures along Balagtas River (Tributary), Brgy. Panginay to Wawa, Balagtas, Bulacan (Phase II)
Location
Panginay, Balagtas, Bulacan
Central Luzon
ZIP: 3016
14.819064, 120.903598
Project Cost
₱79M
₱79,199,187.57
              
                
              
              Project Timeline
            
            Start Date
May 14, 2023
Sun, May 14, 2023
Actual Start
May 14, 2023
Sun, May 14, 2023
Target Completion
April 07, 2024
Sun, Apr 07, 2024
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
Contractor
1 contractor
                
                  
                
                Project Updates
                Updates
                
                  (0)
                
              
              
            No updates yet
Be the first to share an update about this project
Project Updates
1 / 1
Use arrow keys to navigate • Press Esc to close
Loading comments...