Construction of Flood Mitigation Structure along Quitangil River, Sta. 8+750 - Sta. 10+658 (R/S), San Agustin, Magalang, Pampanga
Location
San Agustin, Magalang, Pampanga
Central Luzon
ZIP: 2011
15.232769, 120.691127
Project Cost
₱49M
₱48,940,091.64
Project Timeline
Start Date
March 19, 2023
Sun, Mar 19, 2023
Actual Start
March 19, 2023
Sun, Mar 19, 2023
Target Completion
September 14, 2023
Thu, Sep 14, 2023
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates