Construction of Flood Control Structure along Rio Chico River, Barangay Macamias, Guimba, Nueva Ecija
Location
Macamias, Guimba, Nueva Ecija
Central Luzon
ZIP: 3115
15.626937, 120.708467
Project Cost
₱48M
₱48,010,181.1
Project Timeline
Start Date
February 12, 2023
Sun, Feb 12, 2023
Actual Start
February 12, 2023
Sun, Feb 12, 2023
Target Completion
July 26, 2023
Wed, Jul 26, 2023
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates