Construction of Flood Control Structure along Maasim River, Upig Section, Brgy. Upig, San Ildefonso, Bulacan
Location
Upig, San Ildefonso, Bulacan
Central Luzon
ZIP: 3010
15.022700, 120.970200
Project Cost
₱99M
₱98,998,363.35
Project Timeline
Start Date
May 05, 2024
Sun, May 05, 2024
Actual Start
May 05, 2024
Sun, May 05, 2024
Target Completion
January 12, 2025
Sun, Jan 12, 2025
Source of Fund
1 source
General Appropriations Act FY 2024
Implementing Agency
1 agency
Contractor
1 contractor