Construction of Slope Protection with Steel Sheet Pile Foundation Along Tarlac River Control Right Dike, Colibangbang Section (Package H), Barangay Colibangbang, Paniqui, Tarlac
Location
Colibangbang, Paniqui, Tarlac
Central Luzon
ZIP: 2307
15.634356, 120.541458
Project Cost
₱77M
₱77,199,671.49
Project Timeline
Start Date
April 11, 2023
Tue, Apr 11, 2023
Actual Start
April 11, 2023
Tue, Apr 11, 2023
Target Completion
November 15, 2023
Wed, Nov 15, 2023
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
Contractor
1 contractor