Construction of Reinforced Concrete Flood Control Structure along Balagtas River, Barangay Santol (Purok 1 to Purok 3), Balagtas, Bulacan
Location
Santol, Balagtas, Bulacan
Central Luzon
ZIP: 3016
14.859988, 120.918630
Project Cost
₱77M
₱77,198,851.79
Project Timeline
Start Date
February 27, 2024
Tue, Feb 27, 2024
Actual Start
February 27, 2024
Tue, Feb 27, 2024
Target Completion
June 18, 2024
Tue, Jun 18, 2024
Source of Fund
1 source
General Appropriations Act FY 2024
Implementing Agency
1 agency
Contractor
1 contractor