Construction of Reinforced Concrete Slope Protection Structure along Sapang Balen Creek, Barangay San Ildefonso, Magalang, Pampanga
Location
San Ildefonso, Magalang, Pampanga
Central Luzon
ZIP: 2008
15.256470, 120.687700
Project Cost
₱77M
₱77,183,078.33
Project Timeline
Start Date
February 15, 2024
Thu, Feb 15, 2024
Actual Start
February 15, 2024
Thu, Feb 15, 2024
Target Completion
May 19, 2024
Sun, May 19, 2024
Project Location Map
Location Map
Source of Fund
1 source
General Appropriations Act FY 2024
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project