Construction of Reinforced Concrete Flood Control Structure, Barangay Santa Monica (Purok 6 to Purok 7), Hagonoy, Bulacan
Location
Santa Monica, Hagonoy, Bulacan
Central Luzon
ZIP: 3002
14.838359, 120.737587
Project Cost
₱68M
₱67,549,830.35
Project Timeline
Start Date
April 17, 2024
Wed, Apr 17, 2024
Actual Start
April 17, 2024
Wed, Apr 17, 2024
Target Completion
June 10, 2024
Mon, Jun 10, 2024
Source of Fund
1 source
General Appropriations Act FY 2024
Implementing Agency
1 agency
Contractor
1 contractor