Construction of Flood Control Structure along Rio Chico, Barangay Macamias, Guimba, Nueva Ecija
Location
Macamias, Guimba, Nueva Ecija
Central Luzon
ZIP: 3115
15.619846, 120.697862
Project Cost
₱19M
₱19,105,042.95
Project Timeline
Start Date
March 31, 2024
Sun, Mar 31, 2024
Actual Start
March 31, 2024
Sun, Mar 31, 2024
Target Completion
September 19, 2024
Thu, Sep 19, 2024
Source of Fund
1 source
General Appropriations Act FY 2024
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project