Construction of Flood Mitigation Structure (Drainage), Barangay Ayala, Zamboanga City
Location
Ayala, City of Zamboanga, Zamboanga Del Sur
Zamboanga Peninsula
ZIP: 7008
6.954348, 121.958185
Project Cost
₱4.1M
₱4,132,146.97
Project Timeline
Start Date
February 11, 2024
Sun, Feb 11, 2024
Actual Start
February 11, 2024
Sun, Feb 11, 2024
Target Completion
July 16, 2024
Tue, Jul 16, 2024
Project Location Map
Location Map
Source of Fund
1 source
General Appropriations Act FY 2024
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project
Project Updates
1 / 1
Use arrow keys to navigate • Press Esc to close
Loading comments...