Construction of Siffu River Flood Control Project (Qui-Bur Bridge Abutment "B" Downstream Section), Quirino, Isabela
Location
Quirino, Isabela
Cagayan Valley
ZIP: 3401
17.117008, 121.708950
Project Cost
₱39M
₱39,199,987.54
Project Timeline
Start Date
February 27, 2022
Sun, Feb 27, 2022
Actual Start
February 27, 2022
Sun, Feb 27, 2022
Target Completion
November 17, 2022
Thu, Nov 17, 2022
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project
Project Updates
1 / 1
Use arrow keys to navigate • Press Esc to close