Construction of Flood Control Structure at Brgy. Papan Este, Jones, Isabela
Location
Papan Este, Jones, Isabela
Cagayan Valley
ZIP: 3313
16.534674, 121.799602
Project Cost
₱97M
₱96,500,000.0
Project Timeline
Start Date
March 31, 2022
Thu, Mar 31, 2022
Actual Start
March 31, 2022
Thu, Mar 31, 2022
Target Completion
November 20, 2022
Sun, Nov 20, 2022
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor