Construction of Flood Control Structure along Cagayan River, Centro Norte Section 1, Gattaran, Cagayan
Location
Gattaran, Cagayan
Cagayan Valley
ZIP: 3519
18.067290, 121.643878
Project Cost
₱24M
₱24,499,913.26
Project Timeline
Start Date
February 01, 2022
Tue, Feb 01, 2022
Actual Start
February 01, 2022
Tue, Feb 01, 2022
Target Completion
June 10, 2023
Sat, Jun 10, 2023
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates