Flood Control Infrastructure
Main Portal
Completed
Construction of Cabicungan Flood Control Structure along Cabicungan River, Nagsabaran, Claveria, Cagayan
P00621527LZ
Location
Nagsabaran, Claveria, Cagayan
Cagayan Valley
ZIP: 3519
18.562646, 121.091471
Project Cost
₱20M
₱19,600,000.0
Project Timeline
Start Date
March 27, 2022
Sun, Mar 27, 2022
Actual Start
March 27, 2022
Sun, Mar 27, 2022
Target Completion
December 10, 2022
Sat, Dec 10, 2022
Project Organizations
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
DPWH