Construction of a Seawall, Buguey, Cagayan
Location
Buguey, Cagayan
Cagayan Valley
ZIP: 3511
18.289444, 121.836389
Project Cost
₱4.9M
₱4,940,000.0
Project Timeline
Start Date
April 04, 2023
Tue, Apr 04, 2023
Actual Start
April 04, 2023
Tue, Apr 04, 2023
Target Completion
June 08, 2023
Thu, Jun 08, 2023
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
Contractor
1 contractor