Construction of Cagayan River Flood Control Project, Barangay Cumu, Angadanan, Isabela
Location
Cumu, Angadanan, Isabela
Cagayan Valley
ZIP: 3307
16.766235, 121.753830
Project Cost
₱14M
₱14,479,105.16
Project Timeline
Start Date
March 19, 2023
Sun, Mar 19, 2023
Actual Start
March 19, 2023
Sun, Mar 19, 2023
Target Completion
July 09, 2023
Sun, Jul 09, 2023
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
Contractor
1 contractor