Flood Control Infrastructure
Main Portal
Completed
Construction of Mallig River Flood Control Project (Holy Friday Section), Mallig, Isabela
P00621159LZ
Location
Rang-ayan, Mallig, Isabela
Cagayan Valley
ZIP: 3323
17.171117, 121.642530
Project Cost
₱96M
₱96,448,972.94
Project Timeline
Start Date
June 07, 2022
Tue, Jun 07, 2022
Actual Start
June 07, 2022
Tue, Jun 07, 2022
Target Completion
December 13, 2022
Tue, Dec 13, 2022
Project Organizations
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
DPWH