Construction of Siffu River Flood Control Project (Camaal Section), Phase II, Sta. 0+000 - Sta. 0+400, Barangay Camaal, Quirino, Isabela,
Location
Camaal, Quirino, Isabela
Cagayan Valley
ZIP: 3322
17.121069, 121.662130
Project Cost
₱48M
₱48,232,335.87
              
                
              
              Project Timeline
            
            Start Date
February 26, 2023
Sun, Feb 26, 2023
Actual Start
February 26, 2023
Sun, Feb 26, 2023
Target Completion
July 23, 2023
Sun, Jul 23, 2023
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
Contractor
1 contractor
                
                  
                
                Project Updates
                Updates
                
                  (0)
                
              
              
            No updates yet
Be the first to share an update about this project