Construction of Flood Control and Drainage Structure along Matuno River, Manamtam Section, Bambang, Nueva Vizcaya
Location
Manamtam, Bambang, Nueva Vizcaya
Cagayan Valley
ZIP: 3702
16.392870, 121.067560
Project Cost
₱90M
₱89,745,000.0
Project Timeline
Start Date
March 07, 2024
Thu, Mar 07, 2024
Actual Start
March 07, 2024
Thu, Mar 07, 2024
Target Completion
May 30, 2024
Thu, May 30, 2024
Source of Fund
1 source
General Appropriations Act FY 2024
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project
Project Updates
1 / 1
Use arrow keys to navigate • Press Esc to close
Loading comments...