Rehablitation/Completion of Drainage, Brgy. Ajat, Iguig, Cagayan
Location
Iguig, Cagayan
Cagayan Valley
ZIP: 3504
17.751753, 121.735881
Project Cost
₱2.5M
₱2,475,000.0
Project Timeline
Start Date
August 14, 2024
Wed, Aug 14, 2024
Actual Start
August 14, 2024
Wed, Aug 14, 2024
Target Completion
December 08, 2024
Sun, Dec 08, 2024
Source of Fund
1 source
General Appropriations Act FY 2024
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates