Construction of Mallig River Flood Control Project, Barangay San Juan Phase II, Sta. 1+100 - Sta. 1+900, Quirino, Isabela
Location
San Juan, Quirino, Isabela
Cagayan Valley
ZIP: 3401
17.110284, 121.695213
Project Cost
₱96M
₱96,470,259.43
Project Timeline
Start Date
April 14, 2024
Sun, Apr 14, 2024
Actual Start
April 14, 2024
Sun, Apr 14, 2024
Target Completion
August 13, 2024
Tue, Aug 13, 2024
Source of Fund
1 source
General Appropriations Act FY 2024
Implementing Agency
1 agency
Contractor
1 contractor