Construction of Flood Control and Drainage Structure along Matuno River, Barat Section, Bambang, Nueva Vizcaya
Location
Barat, Bambang, Nueva Vizcaya
Cagayan Valley
ZIP: 3702
16.389320, 121.056250
Project Cost
₱90M
₱89,745,000.0
Project Timeline
Start Date
March 07, 2024
Thu, Mar 07, 2024
Actual Start
March 07, 2024
Thu, Mar 07, 2024
Target Completion
April 14, 2024
Sun, Apr 14, 2024
Source of Fund
1 source
General Appropriations Act FY 2024
Implementing Agency
1 agency
Contractor
1 contractor