Construction of Retention Basin along Estero de Sampaloc Phase III, Manila City
Location
City of Manila
NCR
ZIP: 1008
14.601943, 120.998161
Project Cost
₱49M
₱48,999,662.04
Project Timeline
Start Date
March 23, 2021
Tue, Mar 23, 2021
Actual Start
March 23, 2021
Tue, Mar 23, 2021
Target Completion
August 19, 2022
Fri, Aug 19, 2022
Source of Fund
1 source
General Appropriations Act FY 2021
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project
Project Updates
1 / 1
Use arrow keys to navigate • Press Esc to close