Construction of Drainage System along Sumulong Highway including laterals, Marikina City (Phase I)
Location
Santo Niño, City of Marikina
NCR
ZIP: 1800
14.636162, 121.093866
Project Cost
₱180M
₱183,574,083.6
Project Timeline
Start Date
June 16, 2022
Thu, Jun 16, 2022
Actual Start
June 16, 2022
Thu, Jun 16, 2022
Target Completion
April 23, 2024
Tue, Apr 23, 2024
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor