Construction of Slope Protection at Hagonoy Pumping Station Retarding Pond, Taguig City (Package 3)
Location
Hagonoy, City of Taguig
NCR
ZIP: 1632
14.508831, 121.070023
Project Cost
₱95M
₱94,569,450.51
              
                
              
              Project Timeline
            
            Start Date
February 15, 2022
Tue, Feb 15, 2022
Actual Start
February 15, 2022
Tue, Feb 15, 2022
Target Completion
October 12, 2022
Wed, Oct 12, 2022
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor
                
                  
                