Construction of Flood Control Structure, Magdaong River, Barangay Poblacion, Muntinlupa City
Location
Poblacion, City of Muntinlupa
NCR
ZIP: 1776
14.377988, 121.024208
Project Cost
₱49M
₱48,999,999.54
              
                
              
              Project Timeline
            
            Start Date
March 10, 2022
Thu, Mar 10, 2022
Actual Start
March 10, 2022
Thu, Mar 10, 2022
Target Completion
September 19, 2023
Tue, Sep 19, 2023
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor
                
                  
                
                Project Updates