Construction of Flood Control Structure along Bagumbayan Creek (Muntinlupa Side) Brgy. Sucat, Muntinlupa City
Location
Sucat, City of Muntinlupa
NCR
ZIP: 1770
14.467279, 121.053242
Project Cost
₱49M
₱48,999,647.28
Project Timeline
Start Date
February 08, 2022
Tue, Feb 08, 2022
Actual Start
February 08, 2022
Tue, Feb 08, 2022
Target Completion
April 13, 2024
Sat, Apr 13, 2024
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates