Construction (Completion) of Pump at Pacheco Drainage Main, Tondo, Manila City
Location
Barangay 105, City of Manila
NCR
ZIP: 1012
14.614332, 120.960251
Project Cost
₱24M
₱24,499,986.79
Project Timeline
Start Date
February 16, 2022
Wed, Feb 16, 2022
Actual Start
February 16, 2022
Wed, Feb 16, 2022
Target Completion
September 06, 2023
Wed, Sep 06, 2023
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project
Project Updates
1 / 1
Use arrow keys to navigate • Press Esc to close