Flood Control Infrastructure
Main Portal
Completed
Construction of Revetment Wall along Bangkal Creek, Brgy. Bangkal, Makati City
P00637040LZ
Location
Bangkal, City of Makati
NCR
ZIP: 1233
14.543656, 121.009775
Project Cost
₱39M
₱39,200,000.0
Project Timeline
Start Date
March 21, 2022
Mon, Mar 21, 2022
Actual Start
March 21, 2022
Mon, Mar 21, 2022
Target Completion
October 23, 2022
Sun, Oct 23, 2022
Project Organizations
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
DPWH
Project Updates
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project