Construction of Flood Control Wall along Maysan-Parada Creek, Brgy. Maysan, Valenzuela City
Location
Maysan, City of Valenzuela
NCR
ZIP: 1440
14.699160, 120.984050
Project Cost
₱15M
₱14,695,219.81
Project Timeline
Start Date
February 07, 2022
Mon, Feb 07, 2022
Actual Start
February 07, 2022
Mon, Feb 07, 2022
Target Completion
August 29, 2022
Mon, Aug 29, 2022
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor