Construction of Slope Protection Structure/Bank Improvement/Sheet Piling of Maricaban Creek (Sta. 0+234 to 0+468), Pasay City
Location
Barangay 180, Pasay City
NCR
ZIP: 1302
14.531809, 121.007079
Project Cost
₱58M
₱57,895,380.25
Project Timeline
Start Date
March 01, 2022
Tue, Mar 01, 2022
Actual Start
March 01, 2022
Tue, Mar 01, 2022
Target Completion
September 06, 2022
Tue, Sep 06, 2022
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor