Construction of Slope Protection along Ermitaño Creek, San Juan City
Location
Ermitaño, City of San Juan
NCR
ZIP: 1500
14.606472, 121.037417
Project Cost
₱20M
₱19,599,999.95
Project Timeline
Start Date
March 23, 2022
Wed, Mar 23, 2022
Actual Start
March 23, 2022
Wed, Mar 23, 2022
Target Completion
January 07, 2023
Sat, Jan 07, 2023
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project