Rehabilitation of Drainage System, Brgy. Talon 2, Las Piñas City
Location
Talon Dos, City of Las Piñas
NCR
ZIP: 1747
14.444404, 120.994110
Project Cost
₱20M
₱19,599,999.97
Project Timeline
Start Date
May 26, 2022
Thu, May 26, 2022
Actual Start
May 26, 2022
Thu, May 26, 2022
Target Completion
November 21, 2022
Mon, Nov 21, 2022
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor