Construction of Revetment along Paranaque River Mouth (North Side) Paranaque City
Location
San Dionisio, City of Parañaque
NCR
ZIP: 1700
14.502652, 120.989465
Project Cost
₱99M
₱98,997,516.14
Project Timeline
Start Date
August 13, 2023
Sun, Aug 13, 2023
Actual Start
August 13, 2023
Sun, Aug 13, 2023
Target Completion
November 17, 2024
Sun, Nov 17, 2024
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project