Construction of Flood Mitigation Structure and Groundsill at Manila Memorial Park, North Side, Phase 1, Parañaque City
Location
San Dionisio, City of Parañaque
NCR
ZIP: 1700
14.456781, 121.022185
Project Cost
₱93M
₱92,609,743.96
Project Timeline
Start Date
February 19, 2024
Mon, Feb 19, 2024
Actual Start
February 19, 2024
Mon, Feb 19, 2024
Target Completion
September 15, 2024
Sun, Sep 15, 2024
Source of Fund
1 source
General Appropriations Act FY 2024
Implementing Agency
1 agency
Contractor
1 contractor