Construction of Revetment along San Dionisio River (Phase III), Parañaque City
Location
San Dionisio, City of Parañaque
NCR
ZIP: 1700
14.489820, 120.992760
Project Cost
₱49M
₱48,606,719.37
Project Timeline
Start Date
February 06, 2024
Tue, Feb 06, 2024
Actual Start
February 06, 2024
Tue, Feb 06, 2024
Target Completion
September 17, 2024
Tue, Sep 17, 2024
Source of Fund
1 source
General Appropriations Act FY 2024
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project