CONSTRUCTION OF HARDENED TYPHOON SHELTER HANGAR FOR FIXED WING AIRCRAFT, AIR COMBAT COMMAND (ACC), EAAB, ZAMBOANGA CITY, PHASE III
Location
City of Zamboanga, Zamboanga Del Sur
Zamboanga Peninsula
ZIP: 7000
6.921400, 122.079000
Project Cost
₱14M
₱14,466,412.61
Project Timeline
Start Date
October 03, 2024
Thu, Oct 03, 2024
Target Completion
March 01, 2025
Sat, Mar 01, 2025
Project Location Map
Location Map
Source of Fund
1 source
General Appropriations Act FY 2024
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet