WIDENING OF PERMANENT BRIDGES - TALINGA BR. (B00458MN) ALONG DIPOLOG- SINDANGAN-LILOY RD (PHASE II)
Location
City of Dipolog, Zamboanga Del Norte
Zamboanga Peninsula
ZIP: 7100
8.588600, 123.340600
Project Cost
₱68M
₱67,816,609.97
Project Timeline
Start Date
February 18, 2024
Sun, Feb 18, 2024
Target Completion
October 30, 2024
Wed, Oct 30, 2024
Project Location Map
Location Map
Source of Fund
1 source
General Appropriations Act FY 2024
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates