NETWORK DEVELOPMENT PROGRAM: ROAD WIDENING ALONG MANILA NORTH ROAD, BAMBAN, TARLAC
Location
Bamban, Tarlac
Central Luzon
ZIP: 2317
15.364000, 120.576000
Project Cost
₱95M
₱94,552,174.74
Project Timeline
Start Date
February 15, 2022
Tue, Feb 15, 2022
Actual Start
February 15, 2022
Tue, Feb 15, 2022
Target Completion
June 26, 2023
Mon, Jun 26, 2023
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project