Flood Control Infrastructure
Main Portal
Completed
BASIC INFRASTRUCTURE PROGRAM (BIP) - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURE/FACILITIES - CONSTRUCTION OF FLOOD CONTROL PROJECT ALONG TUAG RIVER, NAGBALAYONG, MORONG, BATAAN
22CA0080
Location
Morong, Bataan
Central Luzon
ZIP: 2108
14.685000, 120.275000
Project Cost
₱3M
₱2,969,998.74
Project Timeline
Start Date
August 10, 2022
Wed, Aug 10, 2022
Actual Start
August 10, 2022
Wed, Aug 10, 2022
Target Completion
April 13, 2023
Thu, Apr 13, 2023
Project Organizations
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
DPWH
Project Updates
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project
Project Updates
1 / 1
Use arrow keys to navigate • Press Esc to close