BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURE/FACILITIES - CONSTRUCTION OF DRAINAGE CANAL ALONG GOV. PASCUAL TO RIVERORANI, BATAAN
Location
Orani, Bataan
Central Luzon
ZIP: 2112
14.804000, 120.541000
Project Cost
₱7.9M
₱7,919,950.09
Project Timeline
Start Date
April 03, 2022
Sun, Apr 03, 2022
Actual Start
April 03, 2022
Sun, Apr 03, 2022
Target Completion
January 29, 2023
Sun, Jan 29, 2023
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor