CONSTRUCTION (COMPLETION) OF MULTI- PURPOSE BUILDING, BARANGAY DILAGUIDI, DILASAG, AURORA
Location
Dilasag, Aurora
Central Luzon
ZIP: 3205
16.466500, 122.129300
Project Cost
₱2.9M
₱2,940,000.0
              
                
              
              Project Timeline
            
            Start Date
February 10, 2022
Thu, Feb 10, 2022
Actual Start
February 10, 2022
Thu, Feb 10, 2022
Target Completion
May 15, 2022
Sun, May 15, 2022
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor
                
                  
                
                Project Updates
                Updates
                
                  (0)
                
              
              
            No updates yet
Be the first to share an update about this project
Project Updates
1 / 1
Use arrow keys to navigate • Press Esc to close
Loading comments...