CONSTRUCTION OF WATER SUPPLY SYSTEM, BRGY. DIANED, DIPACULAO, AURORA
Location
Dipaculao, Aurora
Central Luzon
ZIP: 3203
15.847000, 121.536000
Project Cost
₱9.8M
₱9,800,000.0
Project Timeline
Start Date
February 17, 2022
Thu, Feb 17, 2022
Actual Start
February 17, 2022
Thu, Feb 17, 2022
Target Completion
August 29, 2022
Mon, Aug 29, 2022
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project
Project Updates
1 / 1
Use arrow keys to navigate • Press Esc to close