CONSTRUCTION OF ONE TRAINING COMPLEX (OTC) MAIN FACILITIES, NAVAL STATION LEOVIGILDO GANTIOQUI (NSLG), SAN ANTONIO, ZAMBALES
Location
San Antonio, Zambales
Central Luzon
ZIP: 2206
15.479000, 120.795000
Project Cost
₱49M
₱48,998,169.86
Project Timeline
Start Date
April 03, 2022
Sun, Apr 03, 2022
Actual Start
April 03, 2022
Sun, Apr 03, 2022
Target Completion
January 12, 2023
Thu, Jan 12, 2023
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor