ASSET PRESERVATION PROGRAM, REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, BALER- CASIGURAN RD (BALER-DINADIAWAN) - K0277+420 - K0277+435, K0278+400 - K0278+415, K0278+800 - K0278+815, K0279+700
Location
Dingalan, Aurora
Central Luzon
ZIP: 3207
15.391700, 121.333300
Project Cost
₱3.7M
₱3,743,600.0
Project Timeline
Start Date
May 29, 2022
Sun, May 29, 2022
Actual Start
May 29, 2022
Sun, May 29, 2022
Target Completion
September 11, 2022
Sun, Sep 11, 2022
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project
Project Updates
1 / 1
Use arrow keys to navigate • Press Esc to close
Loading comments...